Chapter 8 – Pre-Startup Safety Review (PSSR)
All processes will go through modifications. So when a modification occurs to a process and is significant enough to require a change in PSI, then a PSSR is required.
The PSSR shall confirm that prior to the introduction of highly hazardous chemical into the process:
Resolved could mean the recommendation is waiting for budget for implementation or the recommended was rejected with rationale.
Here’s were a priority system to prioritize the highest risk recommendations is helpful.
There are two possible way for a PSSR to be implemented: