Maintenance of Waterfront Facilities by Department of the Army - HTML preview

PLEASE NOTE: This is an HTML preview only and some elements such as links or page numbers may be incorrect.
Download the book in PDF, ePub, Kindle for a complete version.

existing stringers which are to remain in the structure.

2.3.1.2 Pile Caps. Decayed or damaged pile caps

Connections between replacement and existing stringers

should be replaced with properly treated members as

shall be made directly over a pile cap and they should

described in 2.1.4. Replacement caps shall be the

be bolted or pinned to the pile cap. Decayed or

same size and length as the original member unless

damaged

redesigned.

2.3.1.3 Braces. Diagonal braces that have been

attacked by fungi or marine borers or have been broken

2-7

index-34_1.png

Figure 2-7. Wood pile replacement.

areas of long stringers can be removed and replaced

deck (see Figure 2-10).

with properly treated new sections. Again, splices

should be made directly over a pile cap; splices in

2.3.1.7 Decking. Decking over which vehicular and

adjacent stringers should be staggered where possible.

pedestrian traffic passes should be replaced when its

A typical splice is shown in Figure 2-8.

top surface becomes excessively uneven, hazardous, or

worn to a point of possible failure. It should be replaced

2.3.1.5 String Pieces. The string piece, sometimes

with properly treated quarter-sawn timber. Spacing

referred to as the curb, bullrail, or backing log, is

between decking planks should be provided for

subjected to much wear and to constant wettings and

ventilation and drainage. Decking for relieving

dryings. Properly treated replacement sections should

platforms which have an earth fill should be laid in a

be long enough to reach between a minimum of two

double layer without spacing between the planks.

bents. New preservative-treated blocks, 2 to 3 inches

thick, should be placed under each replacement section

2.3.1.8 Fire Curtain Walls. Wood fire curtain walls are

on 3-to-4-foot centers to provide for drainage. If any

usually made of two layers of planking which run

part of the lower string piece has deteriorated, the entire

diagonally to one another. All deteriorated planks

piece of timber should be replaced (see Figure 2-9).

should be replaced to restore the wall to its original

condition - as airtight as possible.

2.3.1.6 Chocks. Deteriorated chocks should be

replaced by properly treated, tightly fitting chocks that

are bolted to one string piece or to a waler below the

2-8

index-35_1.png

Figure 2-8. Stringer splice.

2.3.1.9 Fender Piles. Decayed, marine borer attacked,

2.3.1.10 Sheeting. Piers and quay walls may have

or broken fender piles that cannot be adequately

wood sheet pile bulkheads to retain fill on the shore

repaired should be pulled and replaced with a properly

side. Deterioration of these bulkheads results in loss of

treated new pile. Installation of a steel "shoe" on the

fill and settlement of the material above the affected

outer (wearing) surface of each fender pile is

areas. In the early stages of deterioration, repairs can

recommended. Adequate camel logs should be

be made by using a plastic marine splash-zone

provided.

compound, such as an epoxy-polyamide.

2-9

index-36_1.png

Figure 2-9. Repair of string piece.

When deterioration is more extensive, sheet piling is

2.3.1.11 Dolphins. The maintenance of timber dolphins

driven to form a new bulkhead a minimum of 1 foot

includes the replacement of fastenings and any wire

behind the existing one in order to avoid the driving

rope wrapping that has become defective through

frames or wales attached to it. Steel sheet piling, driven

corrosion or wear. The maintenance of a catwalk that

to a minimum of 3 feet below the toe of the deteriorated

connects dolphins includes the replacement of damaged

wood sheeting, is normally used for the new bulkhead.

or deteriorated timbers; steel members should be

The fill at the inside edge is normally removed before

cleaned and painted, or replaced. The repair of

driving the new sheet piling. When this is done, a

dolphins includes replacement or rehabilitation of piles,

concrete cap should be placed over the new sheeting to

wire rope wrappings, and blocking. If it is necessary to

form a seal with the existing construction.

replace any piles, the fastenings should be removed

only as far

2-10

index-37_1.jpg

Figure 2-10. 100% deterioration of chocks, lower wales, and fender piles.

as is necessary to release the piles that are damaged.

are driven, the center cluster should be brought together

Care should be taken to drive the new piles at the

first, fitted, chocked, bolted, and pinned; when all rows

proper angle so that they will not have to be pulled too

have been properly fitted, etc., they are then wrapped

far to fit them in place. The size of piles to be replaced

with wire rope. All cuts in piles for fittings, bolts, and

should be carefully noted, particularly at the head or

wrappings should be thoroughly field-treated with

intermediate point where they are fitted together with the

creosote. These cuts should be avoided if at all

other piles. Much trouble in cutting and fitting the

possible, however, because field treatment with

replacement piles can be avoided by selecting piles with

creosote gives only marginal protection against marine

the proper size head. All replacement piles should be

borer attack.

driven before any are brought together. After all piles

2-11

index-38_1.png

borer attack, a flexible PVC barrier may be installed

(Figure 2-12). An in-place barrier not only prevents

further attack on a pile, but it also creates a stagnant

area between it and the pile surface, thus killing

organisms already present on or within the pile. In this

method, the pile is sheathed with a prefabricated unit

consisting of a 30-mil PVC sheet with a full-length, half-

round apitong wood pole piece attached to each vertical

edge. Lengths of flexible polyurethane foam, 1/2 x 3/6

inch, are stapled about 1 inch from the upper and lower

horizontal edges. When only the intertidal area is to be

sheathed, the PVC wrap is placed around the pile, and

the pole pieces are fitted together with one inserted into

a pocket attached to the bottom of the other. The

excess material is rolled on the combined pole pieces

and tightened around the pile with a special ratchet

wrench. Aluminum alloy nails are driven through the

rolled material and the pole pieces to secure the wrap

Figure 2-11. Replacing tops of piles.

initially. Then rigid plastic bands are nailed at the top

and bottom directly over where the polyurethane foam is

2.3.2 REPAIR

located under the wrap. Additional bands are installed

on equidistant centers between the top and bottom

2.3.2.1 Decayed Bearing Piles. The decayed top of a

bands. For protection extending to the mud line,

wood bearing pile can be repaired by cutting off the

approximately 12 inches of soil is excavated around the

damaged portion and fumigating the exposed cut-off to

pile, and the wrap is placed around the pile, lowered into

destroy any remaining hyphal threads. A section of

the excavated area, and secured as above. Then the

sound timber is installed and secured with epoxy cement

excavated area is backfilled with soil. When it is

or drift pins and fish plates to build the pile to the proper

necessary to wrap a pile that has creosote bleeding from

height (see Figure 2-11).

its surface, a sheet of polyethylene film is stapled to the

pile surface prior to installing the PVC wrap. (Creosote

2.3.2.2 Marine-Borer-Damaged Bearing Piles. Wood

will soften and swell PVC, but it does not affect

bearing piles that have lost 10 to 50% of their cross-

polyethylene.)

sectional area can be repaired by any of several

methods.

2.3.2.2.2 Concrete Barrier. When a diver or ultrasonic

inspection reveals that a pile has lost approximately 15

2.3.2.2.1 Flexible Barrier. When a diver or ultrasonic

to 50% of its cross-sectional area because of marine

inspection reveals that a pile has lost approximately 10

borer attack, a reinforced concrete barrier may be

to 15% of its cross-sectional area because of marine

installed.

2-12

index-39_1.jpg

Figure 2-12. A flexible PVC barrier installed on wooden piles.

Various types of metal, nylon mesh, and pitch-

where undamaged wood is present, and the section is

impregnated fiber tube forms can be used. Two very

removed from the structure. In one patented method, a

important requirements for installations of this type are

specially designed, partly reusable form is clamped to

(1) a tight bottom seal between the form and the pile,

the pile stub and to the pile cap. Grout is pumped

and (2) a grout-dispensing pipe that extends to the very

through a hose connected to a nipple in the lower form

bottom of the form so that seawater within the form can

clamp and is continued until the grout reaches the pile

be pushed up and out by the rising column of pumped-in

cap. When the concrete has set, the upper and lower

grout.

form clamps are removed, and the expendable form

tube is left in place.

Another system uses a reinforced plastic jacket

which is placed to within 1/8 inch of the pile surface. A

2.3.2.3 Braces. A diagonal brace, which extends into

two-component resin mix is prepared, an equal part of

the water and has been lightly attacked by marine

fine sand is added, and this mortar is poured slowly into

borers, can be saved by (1) removing the bolt which

the void to replace the water.

secures it to the pile, (2) wrapping the freed end with 20-

mil flexible PVC sheet in a manner similar to applying

2.3.2.2.3 Replace Section. Replacement of damaged

electrical tape to a cut-off wire, (3) driving the bolt

wood pile sections with a reinforced concrete pile

through the wrapping and through the existing hole, and

section can be accomplished as follows: soil is

(4) rebolting the brace to the pile.

excavated at the mud line, the damaged pile is cut off

2-13

index-40_1.png

Figure 2-13. Fender pile repair.

2.3.2.4 Fender Piles. Fender piles that have been

and bolted in place directly behind the fender pile and

broken between the top and bottom wales can be

between the top and bottom wales. A metal "shoe"

repaired by cutting off the pile just below the break,

(wearing strip) should be attached to the wearing edge

installing a new section of pile, and securing w; n epoxy

of each fender pile (see Figure 2-13).

cement. A strongback (pile or timber section) is fitted

2-14

CHAPTER 3- CONCRETE STRUCTURES

SECTION 1. CONCRETE TECHNOLOGY

3.1.1 DEFINITION OF CONCRETE . Concrete is a

and gravel, crushed rock, or mixtures of them. Other

mass of sand, gravel, crushed rock, or other aggregate

aggregates, such as blast-furnace slags, manufactured

bonded together by a hardened paste of hydraulic

sand, or crushed coral, are used when the more

cement and water. When properly proportioned, mixed,

commonly used aggregate is unavailable. The

and consolidated, these ingredients form a workable

aggregate portion generally constitutes about 75% of the

mass which can be placed into a form of desired size

volume of the concrete. Particle size is usually limited

and shape. The water present reacts with the cement to

to three-fourths the distance between reinforcing bars or

convert the concrete to a hard and durable product.

one-fifth the minimum dimension, and never more than

3/4 inch. Particles of various sizes should be uniformly

3.1.2 COMPONENTS OF CONCRETE

distributed throughout the mass and properly graded for

dense packing. The quality and gradation of aggregate

3.1.2.1 Cement. Cement is a kiln-dried and finely

should conform to ASTM requirements.

pulverized mixture of natural earth materials used as a

bonding ingredient in concrete or mortar. Of the five

3.1.2.3 Water. Water not only changes the concrete

types of cement defined by the American Society for

mixture to a workable consistency suitable for placing in

Testing and Materials (ASTM), only Types II and V

a mold or forms for a desired size and shape, but it is a

should be considered for concrete structures that come

necessary ingredient to react with the cement, called

into contact with seawater. Type V is the recommended

hydration, which converts the cement to a hardened

product for such structures because of its high

mass. The ratio of water to cement (W/C) is largely

resistance to sulfate attack (a form of disintegration

responsible for determining the strength of the concrete.

occurring in seawater and other high salt environments).

This ratio, which excludes water absorbed by the

The more commonly produced Type II, which has a

aggregate, is expressed as a decimal (on a weight ratio

moderate resistance to sulfate attack, can be used when

basis) or as gallons of water per standard 94-pound bag

high cement factors (more than 7-sack) are necessary.

of cement. See Table 3-1 for the relationship between

This will result in low water/cement ratios.

these two methods of expressing W/C. The water used

in mixing concrete must be clean freshwater. Potable

3.1.2.2 Aggregate. Aggregate is the inert filler material

in concrete that permits good physical properties (see

3.1.3) at a low cost. It usually consists of natural sand

3-1

Table 3-1. Relationship Between Methods of

batch of concrete immediately before or during mixing

Expressing Water-to-Cement Ratio

to impart desirable properties to it. Water-reducing

admixtures permit the use of less water to give a

Gallons/Bag

Weight Ratio

concrete mix equal consistency that may result in a final

product of greater strength, watertightness, and

4

0.36

durability. Air-entraining admixtures are used to

4.5

0.40

increase the resistance of hardened concrete to cycles

5

0.44

of alternate freezing and thawing and to improve the

5.5

0.49

workability of the concrete mix. For all concrete

6.0

0.53

structures exposed to seawater, the entrained air

6.5

0.58

content should be between 4-1/2 and 6%. Air

7.0

0.62

entrainment will result in decreased strength, but it can

7.5

0.66

normally be counteracted with more cement. Air

8.0

0.71

entrainment in amounts significantly greater than 6%

8.5

0.75

should be tested for strength. Accelerator admixtures

9.0

0.80

are used to increase the early strength of concrete.

Some accelerator admixtures contain chloride and

Weight Ratio

Gallons/Bag

should only be used for temporary construction. All

admixtures should only be used when necessary.

0.35

3.94

0.40

4.50

3.1.3 DESIRABLE PROPERTIES OF CONCRETE

0.45

5.07

0.50

5.63

0.55

6.20

3.1.3.1 Workability. The concrete composition should

0.60

6.76

be such that it is easily mixed, handled, transported, and

0.65

7.32

placed with vibrators without loss of homogeneity.

0.70

7.88

0.75

8.44

3.1.3.2 Strength. Much of the strength of concrete is

0.80

9.00

related to the amount of mixing water used (W/C ratio).

Thus, the common field practice of adding more water

water is most commonly used; water with a high mineral

to improve workability at a sacrifice in strength should

or salt content, even though it may be called potable,

be avoided. As shown in Figure 3-1, the W/C ratio

may not be suitable.

affects compressive strength much more than tensile

and flexural strengths. Compressive strength increases

3.1.2.4 Admixtures. Admixtures are materials other

with the age of the concrete. The average portland

cement

than cement, aggregate, or water that are added to the

3-2

index-43_1.png

The lower the curing temperature within this range, the

greater the assurance of proper curing. Too rapid a loss

of water at a higher temperature may result in shrinkage

cracks. When concrete is poured at temperatures

appreciably below 50°F, special heating and/or

insulating techniques must be employed to raise the

temperature to a more favorable level.

3.1.3.3 Durability. A durable concrete will exhibit

resistance to weathering, chemical deterioration, and

erosion. Concrete composition is the most important

factor related to durability. The cement content should

be not less than 8 bags per cubic yard, and the

aggregate/cement ratio not less than 2.6 (by weight).

The durability of concrete exposed to freezing and

thawing is enhanced by use of air-entraining admixtures.

Note that newly poured concrete must not be allowed to

freeze.

3.1.3.4 Watertightness. Excess water in the concrete

mix creates voids or cavities which increase

permeability. Thus, a proper W/C ratio is very important

as is prolonged, thorough curing for watertightness.

However, with an 8-sack mix, one should be able to

obtain a proper W/C ratio 0.45 or less.

3.1.4 SPECIAL CONCRETES FOR WATERFRONT

STRUCTURES

3.1.4.1 Prestressed Concrete. Prestressed concrete is

a special type of reinforced concrete containing

stretched tendons of steel (bars, cables, wire ropes).

The steel is considered pretensioned if it is stretched

before the concrete attains initial set. It is considered

Figure 3-1. Effect of water/cement ratio on 28-day

post-tensioned if it is stretched after the hardened

compressive, flexural, and tensile strengths.

concrete has obtained a specified strength; the

unstretched steel is first encased within ducts to prevent

concrete develops about 75% of its 28-day compressive

its bonding to the concrete. If the concrete was steam-

strength after 7 days. After 1 year it is about 150% of

cured, it will not be equally as durable as a concrete that

the 28-day value, and after 5 years, 200% of this value.

was simply water-cured for the same period of time.

The hardening process begins at final set and continues

indefinitely with favorable curing temperatures. The

favorable temperature range extends from 50° to 90°F.

3-3

3.1.4.2 Fiber-Reinforced Concrete. A new approach

The aggregate should be graded as indicated in Table

to reinforcing concrete is the use of steel fibers, about

3-2.

0.014 inch in diameter and 1.5 inches long, uniformly

(6)

The formwork in which the concrete is

distributed and randomly directed throughout the

poured must be rigid, carefully fitted, and designed so

concrete mix. Such fibers can be utilized either in

that no underwater currents can pass through it.

ordinary reinforced concrete or prestressed concrete to

Provision must be made for the seawater displaced by

increase the tensile strength and resistance to cracking.

the concrete to escape from within the form. Timber is

generally the most suitable material for construction of

3.1.4.3 Underwater Concrete. Concrete poured

the formwork. Joints between the formwork and the

underwater must have good workability and, thus,

intact portion of a structure should be caulked.

should meet the following conditions:

(7)

Low temperatures during mixing and

(1)

The mixture must incorporate the proper

curing of concrete (i.e., below 50°F) can delay strength

proportions of sand and gravel (preferably not crushed

development for periods as long as one year and so

material) in a rich paste of portland cement and

should be avoided.

freshwater.

(8)

An enclosed chute or "trunk" should be

(2)

The mixing water must not exceed 5.5

specified so that there is no mixing with water during

gallons per bag of cement. (Mixing water includes the

placement.

water entering the batch in the form of free, surface

moisture on the sand and/or gravel; this free water must,

Table 3-2. Gradation of Aggregates for

therefore, be deducted from the total water to be

Tremie Concrete

added.) If the aggregate particles are surface-dry and

Aggregrate

U.S. Standard