Successful Project Managers Road Map by Mostafa Alshimi - HTML preview

PLEASE NOTE: This is an HTML preview only and some elements such as links or page numbers may be incorrect.
Download the book in PDF, ePub, Kindle for a complete version.

How to use and apply Earned  Value Management

 

Earned Value Management (EVM) Definition

 

Earned Value Management (EVM) helps project managers to measure  project performance. It is a systematic project management process used  to find variances in projects based on the comparison of worked  performed and work planned. EVM is used on the cost and schedule  control and can be very useful in project forecasting. The project baseline  is an essential component of EVM and serves as a reference point for all  EVM related activities. EVM provides quantitative data for project decision  making.

 

To use EVM you need to calculate three types of data:-

 

1. Planned Value (PV): the authorized budget for a planned piece of  work. Sometimes called Budgeted Cost of Work Scheduled  (BCWS).

 

2. Earned Value (EV): the authorized budget for work actually  completed. Sometimes called Budgeted Cost of Work  Performance (BCWP).

 

3. Actual Cost (AC): the costs actually incurred in completing the  work actually achieved (the work as measured by the EV above)  Sometimes called Actual Cost of Work Performed (ACWP).

 

To illustrate how to calculate above data on real example, consider below  tasks:-

 

img5.png

 

img6.png

Consider that today is End of 4/1/2013, so we are expecting the 100% of

Task1, 75% of task 2 and 66% of task 3.

 

Now let us calculate each type of data

 

Planned Value (PV): 100 % of Task1 + 75 % of Task 2 + 66 % of task 3 = (1.0  * 100$) + (0.75 * 500$) + (0.66 * 200$) = 607$

 

Earned Value (EV): 100 % of Task 1+ 50 % of Task 2 + 66 % of task 3 = (1.0  * 100$) + (0.5 * 500$) + (0.66 * 200$) = 482$

 

Actual Cost (AC): Cost spent to achieve the completed percentage for  each task = 110$ + 300$ + 100$ = 510$

 

Having above data only is not beneficial at all until it is used to represent  the variances in the project which will tell you how much you are ahead or  behind schedule and over or under budget.

 

To calculate how much your project has variance in schedule you need to  calculate:-

 

Schedule Variance (SV): it is telling you how much in value your schedule  is varied from planned value

 

SV = EV – PV = 482$ - 607$ = - 125$

 

If SV is positive value then it means you are ahead the schedule by this  value, and vice versa if it negative value then it means you are behind  schedule by this value in other words you need to compensate this value  in your schedule to make SV = 1 which means your schedule is on track.

 

Schedule Performance Index (SPI): it acts like percentage or rate to  describe how your schedule is behaving in terms of ahead or behind  schedule.

 

SPI = EV / PV = 482 / 607 = 0.79

 

If SPI is greater than one then you are ahead the schedule and it is less  than 1 then you are behind schedule.

 

A great use for SPI is the “Trend Analysis” which depends on the  calculated values of SPI at different points of time during the project like  each month, so after 3- 4 months you can draw a graph which will tell you  the trend in your project is either you are covering up and your SPI is  going high to one or you are going more late and you SPI is going more  below 1.0 for each month.

 

img7.jpg

 

img8.jpg

 

Using above calculation and figures you can know how your project is  behaving and how it will continue, but schedule is not necessary reflecting  cost meaning being behind schedule does not mean necessarily being  over budget, so let us talk about cost analysis÷

 

Cost Variance (CV): it is telling how much more / less you spent on the  achieved work.

 

CV = EV – AC = 482$ - 510$ = - 28$

 

If CV is positive then it means you save this amount of money and if it is  negative so it means you spent this amount of money as extra to achieve  this work in other words you are over budget by this amount of money.

 

Cost Performance Index (CPI): it acts like percentage or rate to describe  how your cost/budget is behaving in terms of over or off budget.

 

CPI = EV / AC = 482/510 = 0.94

 

If CPI is greater than one then you are off budget and it is less than 1 then  you are over Budget and you need to find a solution to compensate this  unplanned extra money spent.

 

You can use the same idea of “Trend Analysis” to judge on your project  trend in terms of cost control.

 

Notes (Place Your Notes Here)