Pavement Maintenance Management by Department of the Army - HTML preview

PLEASE NOTE: This is an HTML preview only and some elements such as links or page numbers may be incorrect.
Download the book in PDF, ePub for a complete version.

3-4. Inspection by sampling

summary of each distress and severity level(s) of

a. General. Inspection of every sample unit in a

distress contained in the sample unit. These data are

pavement section may be necessary if exact quantities

used to compute the PCI for the sample unit as outlined

are needed for contracting; however, such inspections

in paragraph 3-5. Figure 3-2 is an example of DA Form require considerable effort, especially if the section is

5145-R showing the summary of distresses for the

large. Because of the time and effort involved, frequent

sample unit.

surveys of an entire section subjected to heavy traffic

volume may be beyond available manpower, funds, and

c. Inspection procedures for asphalt, tar-surfaced,

time. Therefore, sampling plans have been developed to

and/or asphalt over concrete pavement. As with jointed

allow adequate determination of the PCI and M&R

concrete pavements, the pavement section must first be

requirements by inspecting only a portion of the sample

divided into sample units. During either the entire

units in a pavement section. The sampling plans can

section inspection or inspection by sampling, the

reduce inspection time considerably and still provide the

inspector walks over each sample unit, measures each

accuracy required. The number and location of sample

distress type and severity, and records the data on the

units to be inspected is dependent on the purpose of

DA Form 5146-R, Asphalt Pavement Inspection Sheet

inspection. If the purpose is to determine the overall

(fig E-2).

condition of the pavement in the network (e.g., initial

(1)

The equipment needed is a hand

inspection to identify projects, budget needs, etc.), then a

odometer used to measure distress lengths and areas, a

survey of one or two sample units per section may

10-foot straightedge, and a ruler to measure the depth of

suffice. The units should be selected to be

ruts or depressions.

representative of the overall condition of the section. If

(2)

One form is used for each sample unit.

the purpose, however, is to analyze various M&R

One column on the form is used to represent each

alternatives for a given pavement section (e.g., project

identified distress type. The number of that distress type

design, etc.), then more sampling should be performed.

is indicated at the top of the column. Amount and

The following paragraphs present the sampling

severity of each distress identified is listed in the

procedure for this purpose.

appropriate column. An example of a completed DA

b. Determining the number of samples.

Form 5146-R Asphalt Pavement Inspection Sheet is

(1)

The first step in performing inspection by

shown at figure 3-3. Distress No. 6 (depression) is sampling is to determine the minimum number of sample

recorded as 6x4L, which indicates that the depression is

units (n) that must be surveyed. This is done by using

a 6-foot by 4=foot area and of low severity. Distress No.

figure 3-4.

10 (longitudinal and transverse cracking) is measured in

linear feet; 3-2 thus, 10L indicates 10 linear feet of light

cracking, etc. The total distress data are used to

3-2

index-15_1.png

TM 5-623

CONCRETE PAVEMENT INSPECTION SHEET

For use of is form, see TM 5-623; the proponent agency is USACE.

Figure 3-2. An example of a completed DA Form 5145-R, Concrete Pavement Inspection Sheet.

3-3

index-16_1.png

TM 5-623

ASPHALT PAVEMENT INSPECTION SHEET

For use of this form, see TM 5-623; the proponent agency is USACE.

Figure 3-3. An example of a completed DA Form 5146-R, Asphalt Pavement Inspection Sheet.

3-4

index-17_1.png

TM 5-623

(2)

The curves shown in figure 3-4 are used

sampling is complete. However, if the PCI range of the

to select the minimum number of sample units that must

samples taken was found to be 40, it would be

be inspected. This will provide a reasonable estimate of

necessary to go back to figure 34. Start at 20 on the N

the true mean PCI of the section. The estimate is within

scale again, proceed vertically to the curve PCI

plus or minus 5 points of the true mean PCI about 95

range=40, and read 13 on the n scale. In this unusual

percent of the time. When performing the initial

case it would be necessary to survey the additional 4

inspection, the PCI range for a pavement section (i.e.,

samples (9+4 = 13).

lowest sample unit PCI subtracted from the highest

sample unit PCI) is assumed to be 25 for asphalt

(b) Given: Portland cement concrete

concrete (AC) surfaced pavements and 35 for Portland

pavement section with N=30. Find: n.

cement concrete (PCC) surfaced pavements. For

Answer: Start at 30 on the N scale, proceed vertical to

subsequent inspections, the actual PCI range

appropriate curve (PCI range=35) and read 15 on the n

(determined from the previous inspection) is used to

scale.

determine the minimum number of sample units to be

surveyed. As illustrated in figure 3-4, when the total (c) Given: An AC or PCC pavement

number of samples within the section is less than five,

section with N<5. Find: n.

every sample unit should be surveyed. If N is greater

Answer: Survey all sample units.

than five, at least five sample units should be surveyed.

(3)

Examples of first assumption for number

c. Selection of samples. Determining specific

of sample units to be surveyed n follow:

sample units to inspect is as important as determining

(a) Given: Asphalt concrete pavement

the minimum number of samples (n) to be surveyed.

section with total number of sample units, N=20.

The recommended method for selecting the samples is

Find: n.

to choose samples that are equally spaced; however, the

first sample should be selected at random. This

Answer: Start at 20 on the N scale (fig 3-4), proceed technique, known as systematic sampling, is illustrated in

vertically to the appropriate curve (PCI range= 25) and

figure 3-5 and is briefly described below.

read 9 on the n scale. Nine sample units should be

surveyed. If the PCI range is found to be within 25 the

Figure 3-4. Determination of minimum number of sample units to be surveyed.

3-5

index-18_1.png

TM 5-623

Figure 3-5. Example selection of sample units to be surveyed.

(1)

The "sampling interval" (i) is determined

was not selected at random and/or contains distress(es)

by i=N/n, where N=total number of available sample

which are not representative of the section.

units, n=minimum number of sample units to be

(2)

The calculation of the PCI when additional

surveyed, and i is rounded off to the smaller whole

sample units are included is slightly altered and its

number (e.g., 3.6 is rounded to 3).

described in paragraph 3-5.

(2)

The random start (s) is selected at random

between 1 and the sampling interval (i). For example, if

3-5. Calculating the PCI from inspection results

i=3, the random start would be a number from 1 to 3.

a. General. Paragraph 3-4 described two ways of (3)

The sample units to be surveyed are

inspecting a pavement section; i.e., inspecting every unit

identified as s, s+i, s+2i, s+3i, etc. If the selected start is

in the section or inspecting by sampling. Data collected

3, then the samples to be surveyed are 3, 6, 9, 12, etc.

during either method of inspection are used to calculate

(See fig 3-5.) This technique is simple to apply and also the PCI. This paragraph explains how to calculate the

gives the information necessary to establish a PCI profile

PCI for a particular sample unit, and how to calculate the

along the pavement section.

PCI for the entire pavement section. An important item

d. Selection of additional sample units. One of the

in the calculation of the PCI is the "deduct value." A

major objections to sampling is the problem of not

deduct value is a number from 0 to 100, with 0 indicating

including very "poor" or "excellent" sample units which

the distress has no impact on pavement condition, and

may exist in a section. Another problem is the selection

100 indicating an extremely serious distress which

of a random sample which contains nontypical distresses

causes the pavement to fail.

such a railroad crossings, potholes, etc.

b. Calculating sample unit PCI. Calculating the PCI

(1)

To overcome these problems, the

for a sample unit is a simple procedure which involves

inspector should label unusual sample units as additional

five steps (see fig 3-6):

sample units. An additional unit implies that the sample

3-6

index-19_1.png

TM 5-623

Step 1. Inspect sample units: Determine distress types

and severity levels and measure density.

Step 5. Compute pavement condition index (PCI) =100 -CDV for each

sample unit inspected

Figure 3-6. Steps for calculating PCI for a sample unit.

(1) Step 1. Each sample unit is inspected and

individual deduct value. For example, assume that two

distress data recorded on DA Form 5145-R for concrete

distresses were found in an asphalt pavement, one with

or DA Form 5146-R for bituminous pavements as

a deduct value of 50, and the other with a deduct value

described in paragraph 3-3. (See figs 3-2 and 3-3.)

of 10. Using figure C-20, the CDV for q=2 (q = number (2) Step 2. The deduct values are determined

of individual deducts whose value is greater than 5) is

from the deduct value curves for each distress type and

44. Since 44 is lower than 50, the CDV is set equal to

severity. (See app C.)

50.

(3) Step 3. A total deduct value (TDV) is

(5) Step 5. The PCI is computed using the

computed by summing all individual deduct values.

relation PCI = 100 CDV.

(4) Step 4. Once the TDV is computed, the

corrected deduct value (CDV) can be determined from

c. Calculating the PCI for a pavement section. If all

the correction curves (fig C-20 or fig C-40). When sample units in a section are surveyed, the PCI of the

determining the CDV, if any individual deduct value is

section is computed by averaging the PCIs

higher than the CDV, the CDV is set equal to the highest

3-7

TM 5-623

of all its sample units. Inspection by sampling, however,

as follows:

requires a different approach. If all surveyed sample

units are selected randomly, the PCI of the pavement

Density =

number of slabs containing a particular type X 100

section is determined by averaging the PCI of its sample

distress number of slabs in sample unit

units. If any additional sample units are inspected, a

weighted average must be used. The weighted average

For example, two slabs in the pavement sample unit

is computed by using the following equation:

shown in figure 3-2 contained linear cracking (distress 28) at medium severity, so the density is calculated as 2

20X 100, or 10 percent. The deduct values are then

PCIs = (N-A)(PCI1 + A)(PCO1) + A(PCO2)

N

(Equation 3-1)

determined for each distress combination from the

distress deduct value curves given in figures C-21

where PCI

through C-39. The CDV is determined from figure C-40,

s = PCI of pavement section, PCI1 = average

PCI of random samples, PCI

and the PCI is calculated as shown in figure 3-2.

2 = average PCI of

additional samples, N = total number of samples in the

e. Determination of distress quantities for a

section, and A = number of additional samples

pavement section. When a pavement has been

inspected.

inspected by sampling, it is necessary to extrapolate the

quantities and densities of distress over the entire

d. Example calculation of the PCI for a sample unit.

pavement section to determine total quantities for the

The field data sheets described in paragraph 3-3 are section.

always used when calculating the PCI of a sample unit.

(1)

If all sample units surveyed were selected

(1) Asphalt pavement inspection sheet (fig 3-

at random, the extrapolated quantity of a given distress

3).

of a given severity level would be determined as

(a) The difference between calculating

illustrated in the following example for medium-severity

a PCI for an asphalt sample unit and calculating a PCI

alligator cracking:

for a concrete sample unit is in the way the distress

density is determined.

Section Information

1. Density for distresses measured by

Surface type: Asphalt concrete

the square foot is calculated as follows:

Area: 24,500 square feet

Total number of sample units in the section: 10

Density =

distress amount in square feet

sample unit area in square feet

X100

Five sample units were surveyed at random, and the

amount of medium-severity alligator cracking was

2. Density for distresses measured by

determined as follows:

the linear foot (bumps, edge cracking, joint reflection

cracking, lane/shoulder drop off, and longitudinal and

Sample

Sample Unit

Medium-Severity Alligator

transverse cracking) is calculated as follows (see

Unit ID

appendix B for distress definitions):

Number

Area, Square Feet

Cracking, Square Feet

02

2500

100

Density =

distress amount in linear feet

04

2500

200

sample unit area in square feet

X100

06

2500

150

3.

Density for distress measured by number (potholes)

08

2500

50

is calculated as follows:

10

2000

100

Total

Density =

number of potholes

Random

12,000

600

sample unit area in square feet

X100

The average density for medium-severity alligator

(b) After the distress density for each distress

cracking is, therefore, 600/12,000 = 05. The

type/severity combination is calculated, the deduct

extrapolated quantity is determined by multiplying the

values are determined from the distress deduct value

density by the section area, i.e., .05X24,500=1225

curves in figures C-1 through C-19 of appendix C. The square feet.

corrected deduct value (CDV) is determined from figure

(2)

If additional sample units were included in

C-20 and is calculated as shown in figure 3-3.

the survey, the extrapolation process would be slightly

(2) Concrete pavement inspection sheet (fig

different. In the example given in (1) above, assume that

3-2). After inspection, calculate the density of distress sample unit number 01 was surveyed as additional and

that the amount of medium-severity alligator cracking

3-8

TM 5-623

was measured as follows:

Since 2500 square feet were surveyed as additional, the

section’s randomly surveyed area is, therefore, 24,500-

Additional

Sample Unit

Medium-Severity

2500=22,000 square feet. The extrapolated distress

Sample Unit ID

Area, Square FeetAlligator

quantity is obtained by multiplying the distress density by

Cracking,

the section’s randomly surveyed area and then adding

Square Feet

the amount of additional distress. In this example:

01

2500

1000

Extrapolated Distress Quantity =.05 x 22,000 + 1000

Total

=2100 square feet

Additional

2500

1000

3-9

TM 5-623

CHAPTER 4

MAINTENANCE AND REPAIR (M&R) GUIDELINES

4-1. Introduction

that can be used to determine whether variation exists.

M&R needs and priorities are highly related to the PCI,

When a PCI value of a sample unit in the section is less

since the PCI is determined by distress information

than the sample unit critical PCI value, a localized

which is a key factor in establishing pavement M&R

random variation exists. For example, if the mean PCI of

requirements. This chapter describes how to do a

a section is 59, any sample unit with a PCI of less than

payment evaluation, how to determine feasible M&R

42 should be identified as a localized bad area by circling

alternatives, and how to establish M&R priorities. These

"Yes" under item 2a on the form. This variation should

guidelines should be based on the PCI, with

be considered when determining M&R needs.

consideration given to other important factors including

Systematic variation occurs whenever a large,

pavement load-carrying capacity. Nondestructive

concentrated area of a section has significantly different

pavement testing techniques may be used in this load-

condition. For example, if traffic is channeled into a

carrying capacity evaluation. A specific M&R alternative

certain portion of a large parking lot, that portion may

can often be selected for a pavement section that is in

show much more distress or be in a poorer condition

very good or excellent condition without a life-cycle cost

than the rest of the area. Whenever a significant amount

analysis. In cases where a life-cycle cost analysis is

of systematic variability exists within a section, the

necessary to select among feasible alternatives, the live-

section should be subdivided into two or more sections.

cycle cost analysis method described in chapter 5 should In that example being considered (fig 4-1) there was no be used.

localized random or systematic variation, so "No" was

circled at both lines 2a and 2b.

4-2. Pavement evaluation procedure

c. Rate of deterioration of condition-PCI. Both the

Evaluation is performed on a section-by-section basis

long and short-term rate of deterioration of each

since each section represents a unit of the pavement

pavement section should be checked. The long-term

network that is uniform in structural composition and

rate is measured from the time of construction or time of

subjected to consistent traffic loadings. It is necessary to

last overall M&R (such as an overlay). The rate is

make a comprehensive evaluation of pavement condition

determined as low, normal, or high using figures 4-3

before rational determination of feasible M&R

through 4-6. The figures are for the following four alternatives can be made. A step-by-step description of

payment types respectively: asphalt concrete (AC)

how to complete the DA Form 5147-R, Section

pavements, AC overlay over AC pavements, Portland

Evaluation Summary (fig. E-3) is given below. An cement concrete (PCC) pavements, and AC overlay over

example of a completed DA Form 5147-R is shown at

PCC pavements. Development of the curves delineating

figure 4-1.

the low, normal, and high rate of deterioration was based

a. Overall condition. The PCI of a pavement

on field data from Fort Eustis, Virginia. For example, an

section describes the section’s overall condition. The

AC pavement that is 20 years old with a PCI of 50 is

PCI, and thus the section condition rating (e.g., good or

considered to have a high long-term rate of deterioration

very good), is based on many field tests and represents

with respect to other AC pavements. Short-term

the collective judgment of experienced pavement

deterioration (i.e., a drop in PCI during the last year)

engineers. In turn, the overall condition of the section

should also be determined since a high short-term

correlates highly with the needed level of M&R. In figure

deterioration rate can indicate the imminent failure of a

4-1 the PCI of the section under consideration was 15, pavement section (fig. 4-7). In general, whenever the so that number was recorded on line 1 and the

PCI of a section decreases by 7 or more PCI points in a

appropriate rating-"very poor"-circled.

year, the deterioration rate should be considered high. If

b. Variations of the PCI within section. PCI

the loss in PCI points is 4 to 6, the short-term

variation within a section can occur on a localized

deterioration rate should be considered normal. It

random basis, and/or a systematic basis. Figure 4-2,

which was developed